r/Decks • • 4d ago

Structural integrity?

Hello. This is a brand new deck system as of 2 months ago. I noticed that not only were 2/3 horizontal supports off center, but also, 2 joist hangars are snapped.

I live in MN and this is the code requirements
https://www.dli.mn.gov/sites/default/files/pdf/res-decks.pdf

I contacted the builder and he said the support posts didn’t move (despite obvious slide marks) or shift. He also said it was nailed on the end where the broken joists are and it was done so to make it straight.

It seems it isn’t or wasn’t square to begin with and should a single 6” x 6” horizontal support been used rather than 3 2” x 6” ’s?

Vertical and horizontal cracks on wood too?

Thanks for feedback.

Thanks for the feedback all:

Seeing as work needs to be done, several questions:

  1. What is the best way to lift the deck platform to add/adjust horizontal beams?
  2. The builder insists the vertical supports didn’t move, what else would explain the misalignment?
  3. Best way to secure end/mid posts attachment is Simpson Ties?
  4. Do the 3 horizontal beams need to be bound together?
  5. Anything else besides the obvious?

Appreciated much!

514 Upvotes

602 comments sorted by

View all comments

Show parent comments

2

u/kevingrays 3d ago

100% they should have used a post to beam connector. Those ties he used are for vertical hold down, usually rafters or joists. The beam and has definitely shifted on the one side. If this contractor is licensed, you can report them if you're not getting the deck built to code.

1

u/Nanas_700k 3d ago

Hurricane ties… insanely incorrect use of them by contractor holy shit.