Brief outline; McArthur Avenue, between Olmstead Street and St. Laurent Boulevard. This critical infrastructure is essential for maintaining the long-term stability of the electrical distribution system in the area. The project has an estimated completion date of February 12, 2026.

Impacted streets: Brant Street, Dieppe Street, Donald Street, Lacasse Avenue, Lafontaine Avenue, McArthur Avenue, Moorvale Street, Mutual Street and Olmstead Street

Project start date: June 29, 2026

Project end date: February 12, 2027

Contractor on site: K-Line Group of Companies