How does it look? Phase 3 of 5.
i started with an unusable bumpy space, graded it, put a pad for a shed, a retaining wall, a pad for a small patio and another retaining wall.
i have 3 drainage pipes, one at the back, and then under each wall.
phase 1 was grade, phase 2 was the drainage, phase 3 the walls
next phase is to backfill the walls (glue is curing) and then shed goes at top, then patio at the bottom.
This is all DIY and I have an office job and little experience in this. So far I have bought 15 cu yards of dirt, 10 cu yards of 3/4in stone, and 5 cu yds of quarry dust.